Friday, November 19, 2010

North Dock and Garage Doors


The wooden dock on the North End of the building is being replaced with a new concrete dock that will be used as a patio. Glass roll-up garage doors are being installed. This will be a great way to let the outside in during the spring and fall.

Friday, November 12, 2010

Interior build-out & Paving





Most all of the interior walls are built now, and drywall hanging/finishing is going quickly. The concrete floor is being sealed and has a tremendous shine. Paving has also begun.

Thursday, November 4, 2010

Walls, Floors and Paint




The interior build-out is moving quickly now. The shell walls are painted, partition walls are going up, and the wood floor is being refinished. The original wood floor that remains is being sanded and sealed while the areas that were repaired are being stained to match the old as closely as possible. Electrical rough-in and HVAC duct work is progressing well. Site work and paving will start this week and should be complete by the end of this month.