A mad dash to the finish. Cubes are starting to be set-up and we are still putting the finishing touches on. Floors received the final coat this weekend, and Griffin will be moving in over the weekend.
Tuesday, January 25, 2011
Set-up time
A mad dash to the finish. Cubes are starting to be set-up and we are still putting the finishing touches on. Floors received the final coat this weekend, and Griffin will be moving in over the weekend.
Open House
Saturday, January 22, 2011
Bowling Alley
Tuesday, January 4, 2011
Exterior Update and Landscaping
HVAC
Saturday, December 11, 2010
Stone Wall - Parking Area
The North Parking lot required a few retaining walls. The "cut" walls were built with the old stones that once supported the building foundation. During renovation, several piers had to be replaced mostly due to water damage. Once the foundation dirt was removed, it was discovered that the piers were supported on poured concrete footings (thankfully...), but they had also intermittently supported the structure with these stones. Most had rolled away from the structure and were loose in the basement. They were cleaned out as repairs were made. Instead of hauling them to the dump, they were reused to create retaining walls. Great work from our stone mason!
North Side Progress
Interior Paint - School House Windows
First coats of paint are going on the walls and the refurbished school house windows are being installed. About 50 of these windows lived in the basement of Sawtooth for over 40 years. As they were being refurbished, one had been inscribed with a knife reading "I hate you Miss Wilson". I'm sure Miss Wilson is long gone, and the author probably has grandchildren now, but the message lives on at Sawtooth!
The view down the long hall is looking South to North down Front Street.
Friday, December 10, 2010
East View
Friday, November 19, 2010
North Dock and Garage Doors
Friday, November 12, 2010
Interior build-out & Paving
Thursday, November 4, 2010
Walls, Floors and Paint
The interior build-out is moving quickly now. The shell walls are painted, partition walls are going up, and the wood floor is being refinished. The original wood floor that remains is being sanded and sealed while the areas that were repaired are being stained to match the old as closely as possible. Electrical rough-in and HVAC duct work is progressing well. Site work and paving will start this week and should be complete by the end of this month.
Thursday, October 21, 2010
Wood Sealer, Drywall and Build-out
The interior wood timbers were coated with a clear sealer. The process deepened the wood color just slightly and really brought out the grain to give a rich appearance. 90% of the shell drywall is complete. The North, South, and East walls all received double layer drywall for more noise reduction. The electrical and mechanical build-out work has begun.
Thursday, October 14, 2010
Insulation - Flash & Batt
Friday, October 8, 2010
Concrete Complete
Wednesday, September 29, 2010
East Side Glow
Concrete Pour
Friday, September 3, 2010
Roof, Siding, and Windows
The roof work has begun, windows are being installed and siding is nearing completion. The building will be dried in very soon, so that the interior construction can begin. The ceiling is being insulated from above the deck. We are installing ISO board insulation onto the existing deck and then "rebuilding" the new deck on top of the ISO. Once complete, it will be a well insulated, efficient system, while preserving the original wood slat roof structure from the inside. We have had a good stretch of dry weather, hopefully it will continue for about 2 more weeks.
Sandblasting Before and After