Tuesday, January 25, 2011

Set-up time



A mad dash to the finish. Cubes are starting to be set-up and we are still putting the finishing touches on. Floors received the final coat this weekend, and Griffin will be moving in over the weekend.

Open House


A picture of the evite for the Grand Opening. Great job by the Bradford group being very creative with the iPhone photos.

Saturday, January 22, 2011

Bowling Alley


This is one of the many contributions from our architect, Nick Dryden. He made this counter top out of reclaimed bowling alley wood from Melrose Lanes. This is the coffee bar.

Tuesday, January 4, 2011

Exterior Update and Landscaping




Canopies on the North End are built, and parking lot lights are installed. Landscaping on the South End is starting to be planted.

HVAC




Most all of the spiral duct work is installed. The supply and return ducts in the basement are massive! View down the hall is looking down Back Street.

Saturday, December 11, 2010

Stone Wall - Parking Area



The North Parking lot required a few retaining walls. The "cut" walls were built with the old stones that once supported the building foundation. During renovation, several piers had to be replaced mostly due to water damage. Once the foundation dirt was removed, it was discovered that the piers were supported on poured concrete footings (thankfully...), but they had also intermittently supported the structure with these stones. Most had rolled away from the structure and were loose in the basement. They were cleaned out as repairs were made. Instead of hauling them to the dump, they were reused to create retaining walls. Great work from our stone mason!

North Side Progress


Starting to see the North End come to life. Here's a progress shot, before and...nearly... after....

Interior Paint - School House Windows



First coats of paint are going on the walls and the refurbished school house windows are being installed. About 50 of these windows lived in the basement of Sawtooth for over 40 years. As they were being refurbished, one had been inscribed with a knife reading "I hate you Miss Wilson". I'm sure Miss Wilson is long gone, and the author probably has grandchildren now, but the message lives on at Sawtooth!

The view down the long hall is looking South to North down Front Street.

Friday, December 10, 2010

East View



This is a daytime and nighttime view of the East Side of the building. Windows are glowing and a view of downtown.

Friday, November 19, 2010

North Dock and Garage Doors


The wooden dock on the North End of the building is being replaced with a new concrete dock that will be used as a patio. Glass roll-up garage doors are being installed. This will be a great way to let the outside in during the spring and fall.

Friday, November 12, 2010

Interior build-out & Paving





Most all of the interior walls are built now, and drywall hanging/finishing is going quickly. The concrete floor is being sealed and has a tremendous shine. Paving has also begun.

Thursday, November 4, 2010

Walls, Floors and Paint




The interior build-out is moving quickly now. The shell walls are painted, partition walls are going up, and the wood floor is being refinished. The original wood floor that remains is being sanded and sealed while the areas that were repaired are being stained to match the old as closely as possible. Electrical rough-in and HVAC duct work is progressing well. Site work and paving will start this week and should be complete by the end of this month.

Thursday, October 21, 2010

Wood Sealer, Drywall and Build-out

The interior wood timbers were coated with a clear sealer. The process deepened the wood color just slightly and really brought out the grain to give a rich appearance. 90% of the shell drywall is complete. The North, South, and East walls all received double layer drywall for more noise reduction. The electrical and mechanical build-out work has begun.

Thursday, October 14, 2010

Insulation - Flash & Batt



The insulation of the walls has begun. The envelop is receiving a 1" foam insulation with an R-11 value and an additional 6" of batt insulation equivalent to R-19, for a total around R-30. This is being done for both energy efficiency and noise reduction. The impact was immediately noticeable.

Friday, October 8, 2010

Concrete Complete


The concrete cap is complete and the floor is uniform across the entire building. The finish turned out great, and the reflectivity and uniformity makes the space feel really large. Once it is sealed, it should really shine.

Wednesday, September 29, 2010

East Side Glow


With all of the windows in on the East side of the building, the sun reflects off of the wood roof deck creating a great, warm glow.

South End Progress


Entry location change and canopy on the South End now complete.

Concrete Pour



The concrete pour for the west half of the building started today. Roof trim work is nearing completion and all of the windows are in. Building is now DRY!

Friday, September 3, 2010

Roof, Siding, and Windows





The roof work has begun, windows are being installed and siding is nearing completion. The building will be dried in very soon, so that the interior construction can begin. The ceiling is being insulated from above the deck. We are installing ISO board insulation onto the existing deck and then "rebuilding" the new deck on top of the ISO. Once complete, it will be a well insulated, efficient system, while preserving the original wood slat roof structure from the inside. We have had a good stretch of dry weather, hopefully it will continue for about 2 more weeks.

Sandblasting Before and After



All of the wood has been sandblasted, an incredible difference. Here are some good before and after photos.